1. A can do a piece of work in 10 days and B can do it in 15 days. How many days will they take to complete it together?
- A5 days
- B6 days
- C7 days
- D8 days
Show answer
Answer: B
Combined rate=1/10+1/15=1/6. So together they take 6 days.